The Buildings substructure involved Structural Framing Only.

Design Brief
Britannia were tasked to design a Standing Seam Aluminium Roofing System including
Structural Decking, Roof Insulation, Guttering & Fascias, completed with Sun Pipes &
Wind Catchers.

Roofing
Single Spanning Decking 0.88mm thick fixed to Hot Rolled UB Steel Rafters.
A complex insulation build-up was used to acheive the 0.15 U Value required.
A combination of VCL & EPDM was used to acheive the Air Seal requirment.
Roof Halters we laid on a Diagonal Sub Purlin fixed to the Decking at each corrugation
to evenly distribute loadings acorss the Structural Decking.
The External Standing Seam Roof Sheet was ARS Coated, a combination of factory
formed Tapered Sheets & Welded Intersections were adopted to acheive the curving Roof
on Plan. The Roofing was completed with Aluminium Gutters, Wind Catchers & a matching
PPC Coated Fascia & Soffit System.

Main contractor

Lend Lease
20 Triton Street
Regent's Place
London
NW1 3BF

Architect 

HLM Architects
2nd Floor
Ailsa Court
121 West Regent Street
GLasgow
G2 2SD

Download case study as PDF

 BP09_Combined_Mess_1405_Britannia.pdf